A0 Motorway: Bucharest Ringroad

Length: 100.7 km. Status:

Color map: Open (42%); under construction (58%); planned (0%).

The Bucharest Ringroad has a proposed length of 100km.

The Southern part is split into three sections for which contractors were selected in April - May 2019:

  • Section 1, A2 - CF902 (Jilava), 16.9km, contractor Alsim Alarko Sanayi Tesisleri ve Ticaret AS, price 830,679,662.15 RON (excluding VAT). Contract signed in August 2019. A section of 6.00km between Popesti Leordeni and CF902/Jilava opened in April 2024, remainder opened in July 2024
  • Section 2, CF902 (Jilava) - DN6, 16.3km, contractor Alsim Alarko Sanayi Tesisleri ve Ticaret AS, price 750,849,942.12 RON (excluding VAT). Contract signed in March 2019. 10.00km between DN5 and DN6 opened in December 2023, the remaining 6.30km between CF902/Jilava and DN5 opened in April 2024
  • Section 3, DN6 - A1, 17.97km, contractors Aktor SA - Euro Construct Trading SRL, price 853,422.022,52 RON (excluding VAT), execution duration: 42 months. Contract signed. The contract was taken over completely by Aktor SA.
The Northern part is split into four sections:
  • Section 1, DJ601 - DN1 (Corbeanca), 17.5km, contractor Impresa Pizzarotti - Retter Project Management, price: 815.08 Million RON excluding VAT. Duration: 12 months for design, 22 months for construction. Contract signed in September 2023
  • Section 2, DN1 (Corbeanca) - DN2 (Afumati), 19.0km, contractor: the consortium of SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price: 831,920,653.34 excluding VAT, 12 months for design, 22 months for construction. Contract signed in May 2021. 9.5km between DN1 and A3 opened in November 2023
  • Section 3, DN2 (Afumati) - DN3 (Cernica), 8.6km, contractor selected in November 2022: China Civil Engineering Construction Corporation, price 397,996,117.63 RON excluding VAT, 12 months for design, 18 months for construction. Contract signed in March 2023
  • Section 4, DN3 (Cernica) - A2, 4.47km, contractor: the consortium SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price 312.6 Million RON excluding VAT, 12 months for design, 18 months for construction. Contract signed in August 2020.

For detailed information please choose a section from the list below:

SectionStatusOpening
South: I.A2 - CF902 (Jilava)OpenApr.2024, Jul.2024
South: II.CF902 (Jilava) - DN6, Section 2OpenDec.2023, Apr.2024
South: III.DN6 - A1Under construction2024
North: I.DJ601 - DN1 (Corbeanca)Under construction2026
North: II.DN1 (Corbeanca) - DN2 (Afumati)Partially open, remainder under construction2023,2025
North: III.DN2 (Afumati) - DN3 (Cernica)Under construction2025
North: IV.DN3 (Cernica) - A2Under construction2025

South: I.A2 - CF902 (Jilava)

Status: Open

Length: 16.9km

Opening Date: Apr. 2024 for 6.0km, Jul. 2024 for remainder



Back to A0 sections list

South: II.CF902 (Jilava) - DN6

Status: Open

Length: 16.3km

Opening Date: Dec 2023 for 10.0km, 2024 for 6.3km



Back to A0 sections list

South: III.DN6 - A1

Status: Under construction, contract signed in April 2019

Length: 17.97km

Opening Date: 2024



Back to A0 sections list

North: I.DJ601 - DN1 (Corbeanca)

Status: Under construction, contract signed in September 2023

Length: 17.5km


Opening date: 2026


Inapoi la lista tronsoane A0


North: II.DN1 (Corbeanca) - DN2 (Afumati)

Status: 9.5km between DN1 and A3 opened in November 2023, remained under construction

Length: 19.0km


Opening date: November 2023 for 9.5km between DN1 and A3, 2025 for the remainder


Inapoi la lista tronsoane A0


North: III.DN2 (Afumati) - DN3 (Cernica)

Status: Under construction

Length: 8.6km


Opening date: 2025


Inapoi la lista tronsoane A0


North: IV.DN3 (Cernica) - A2

Status: Under construction

Length: 4.47km


Opening date: 2025


Inapoi la lista tronsoane A0