A0 Motorway: Bucharest Ringroad
Length: 100.7 km. Status:
Color map: Open (42%); under construction (58%); planned (0%).
The Bucharest Ringroad has a proposed length of 100km.
The Southern part is split into three sections for which contractors were selected in April - May 2019:
- Section 1, A2 - CF902 (Jilava), 16.9km, contractor Alsim Alarko Sanayi Tesisleri ve Ticaret AS, price 830,679,662.15 RON (excluding VAT). Contract signed in August 2019. A section of 6.00km between Popesti Leordeni and CF902/Jilava opened in April 2024, remainder opened in July 2024
- Section 2, CF902 (Jilava) - DN6, 16.3km, contractor Alsim Alarko Sanayi Tesisleri ve Ticaret AS, price 750,849,942.12 RON (excluding VAT). Contract signed in March 2019. 10.00km between DN5 and DN6 opened in December 2023, the remaining 6.30km between CF902/Jilava and DN5 opened in April 2024
- Section 3, DN6 - A1, 17.97km, contractors Aktor SA - Euro Construct Trading SRL, price 853,422.022,52 RON (excluding VAT), execution duration: 42 months. Contract signed. The contract was taken over completely by Aktor SA.
The Northern part is split into four sections:
- Section 1, DJ601 - DN1 (Corbeanca), 17.5km, contractor Impresa Pizzarotti - Retter Project Management, price: 815.08 Million RON excluding VAT. Duration: 12 months for design, 22 months for construction. Contract signed in September 2023
- Section 2, DN1 (Corbeanca) - DN2 (Afumati), 19.0km, contractor: the consortium of SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price: 831,920,653.34 excluding VAT, 12 months for design, 22 months for construction. Contract signed in May 2021. 9.5km between DN1 and A3 opened in November 2023
- Section 3, DN2 (Afumati) - DN3 (Cernica), 8.6km, contractor selected in November 2022: China Civil Engineering Construction Corporation, price 397,996,117.63 RON excluding VAT, 12 months for design, 18 months for construction. Contract signed in March 2023
- Section 4, DN3 (Cernica) - A2, 4.47km, contractor: the consortium SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price 312.6 Million RON excluding VAT, 12 months for design, 18 months for construction. Contract signed in August 2020.
For detailed information please choose a section from the list below:
South: I.A2 - CF902 (Jilava)
Status: Open
Length: 16.9km
Opening Date: Apr. 2024 for 6.0km, Jul. 2024 for remainder
|
Back to A0 sections list
South: II.CF902 (Jilava) - DN6
Status: Open
Length: 16.3km
Opening Date: Dec 2023 for 10.0km, 2024 for 6.3km
|
Back to A0 sections list
South: III.DN6 - A1
Status: Under construction, contract signed in April 2019
Length: 17.97km
Opening Date: 2024
|
Back to A0 sections list
North: I.DJ601 - DN1 (Corbeanca)
Status: Under construction, contract signed in September 2023
Length: 17.5km
Opening date: 2026
|
Inapoi la lista tronsoane A0
North: II.DN1 (Corbeanca) - DN2 (Afumati)
Status: 9.5km between DN1 and A3 opened in November 2023, remained under construction
Length: 19.0km
Opening date: November 2023 for 9.5km between DN1 and A3, 2024 for the remainder
|
Inapoi la lista tronsoane A0
North: III.DN2 (Afumati) - DN3 (Cernica)
Status: Under construction
Length: 8.6km
Opening date: 2025
|
Inapoi la lista tronsoane A0
North: IV.DN3 (Cernica) - A2
Status: Under construction
Length: 4.47km
Opening date: 2024
|
Inapoi la lista tronsoane A0