130km.ro

Welcome. On this site you can view information concerning existing and future Romanian motorways.



A13 Motorway: Sibiu - Brasov - Bacau

Length: 300km (estimated). Status:

Color map: Open (0%); under construction (23%); planned (77%).

A13 is a proposed motorway following the route Sibiu - Fagaras and then continuing to Brasov - Bacau.

For detailed information please choose a section from the list below:

SectionStatusOpening
I.Sibu - FagarasUnder construction2027
II. Other sectionsplanned-

I.Sibiu - Fagaras

Status: Under construction

Length: 68.04km

Opening Date: 2027


This route is split into four sections:
  • Section 1 Boita (A1) - Avrig/Marsa (DJ105G), 14.25km. Contractor selected in September 2023: MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S., price: RON 1.90 billion RON (excl. VAT), design duration: 12 months, execution duration: 36 months. Contract signed in November 2023. Opening date: 2027.
  • Section 2 Avrig/Marsa - Arpasu de Jos, 19.92km. Contractor selected in October 2023: MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S., price: 1.54 billion RON (excl. VAT), design duration: 12 months, execution duration: 36 months. Contract signed in November 2023. Opening date: 2027.
  • Section 3 Arpasu de Jos - Sambata de Sus, 17.61km. Contractor selected in June 2023: MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S., price: 1.77 billion RON (excl. VAT), design duration: 12 months, execution duration: 36 months. Contract signed in August 2023. Opening date: 2027.
  • Section 4 Sambata de Sus - Fagaras, 16.26km. Contractor selected in May 2023: the consortium Makyol Insaat Sanayi Turizm VE Ticaret AS - Yapi Merkezi Insaat VE Sanayi AS, price: RON 1.19 billion (excl. VAT), design duration: 12 months, execution duration: 36 months. Contract signed in September 2023. Opening date: 2027.


Back to A13 sections list

II.Other sections

Status: -

Length: -

Opening Date: -



Back to A13 sections list

(C) 130km.ro / Back to Romanian Motorways list