A13 Motorway: Sibiu - Brasov - Bacau
Length: 300km (estimated). Status:
Color map: Open (0%); under construction (23%); planned (77%).
A13 is a proposed motorway following the route Sibiu - Fagaras and then continuing to Brasov - Bacau.
For detailed information please choose a section from the list below:
I.Sibiu - Fagaras
Status: Under construction
Length: 68.04km
Opening Date: 2027
This route is split into four sections:
- Section 1 Boita (A1) - Avrig/Marsa (DJ105G), 14.25km. Contractor selected in September 2023: MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S., price: RON 1.90 billion RON (excl. VAT), design duration: 12 months, execution duration: 36 months. Contract signed in November 2023. Opening date: 2027.
- Section 2 Avrig/Marsa - Arpasu de Jos, 19.92km. Contractor selected in October 2023: MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S., price: 1.54 billion RON (excl. VAT), design duration: 12 months, execution duration: 36 months. Contract signed in November 2023. Opening date: 2027.
- Section 3 Arpasu de Jos - Sambata de Sus, 17.61km. Contractor selected in June 2023: MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S., price: 1.77 billion RON (excl. VAT), design duration: 12 months, execution duration: 36 months. Contract signed in August 2023. Opening date: 2027.
- Section 4 Sambata de Sus - Fagaras, 16.26km. Contractor selected in May 2023: the consortium Makyol Insaat Sanayi Turizm VE Ticaret AS - Yapi Merkezi Insaat VE Sanayi AS, price: RON 1.19 billion (excl. VAT), design duration: 12 months, execution duration: 36 months. Contract signed in September 2023. Opening date: 2027.
|