130km.ro

Welcome. On this site you can view information concerning existing and future Romanian motorways.



A1 Motorway Bucharest - Nadlac

Length: 578.48 km. Status:

Color map: Open (79%); under construction (21%); planned (0%).

The A1 Motorway A1 starts in Bucharest and ends at Nadlac (located on Romania's border with Hungary). It goes through the following cities: Pitesti, Sibiu, Deva, Timisoara and Arad.
For more information click on an individual section:

SectionStatusOpening
I.Bucharest - PitestiOpen1973
II.Pitesti - SibiuPartially under construction, partially openDec 2010, Dec 2022, Dec 2024, 2025-2027
III.Sibiu - OrastieOpenDec 2013, Nov 2014, Oct 2016
IV.Orastie - DevaOpenDec 2012, May 2013
V.Deva - LugojPartially open, remainder under constructionDec 2013, Dec 2015, Mar 2017, Aug 2019, Dec 2019, 2026
VI.Lugoj - TimisoaraOpenOct 2012, Dec 2015
VII.Timisoara - AradOpenDec 2011, Jun 2012
VIII.Arad - NadlacOpenDec 2014, Jul 2015

I.Section Bucharest - Pitesti

Status: Open

Length: 109.60 km


Opening date: 1973 for Bucharest - Pitesti (96.00km). Pitesti bypass (13.60km) and underground tunnel for connection with DN7 in Bascov added in 2007.


Back to A1 sections list


II.Section Pitesti - Sibiu

Status: Partially open, partially under construction

Length: 122.11 km + 17.56 km (Sibiu Bypass)

Opening deadline: December 2010 for Sibiu bypass, December 2022 for section 1, December 2024 for partial route on section 5 (Bascov-Baiculesti), 2025-2027 for difference on section 5 and sections 2-4


  • Sibiu bypass (Selimbar - Sura Mica), 17.56km. Opened in December 2010.
  • Section 1 Sibiu - Boita, 13.17km. Contractor: Porr; Cost: 613 Million RON (excluding VAT); duration: 12 months for design, 3 years for execution. Contract signed in April 2019. Opened in December 2022
  • Section 2 Boita - Cornetu, 31.33km. Contractor: the consortium Mapa Insaat Ve Ticaret AS - Cengiz Insaat Sanayi Ve Ticaret; cost: RON 4.250 billion (excluding VAT); duration: 18 months for design, 50 months for execution. Contract signed in February 2022. Opening date: 2027
  • Section 3 Cornetu - Tigveni, 37.40km. Contractor: the consortium Astaldi - Tancrad; Cost: 5.32 billion RON (excl. VAT); duration: 12 months for design, 45 months for execution. Contract signed in August 2022. Opening date: 2027
  • Section 4 Tigveni - Curtea de Arges, 9.86km. Tender launched in March 2019. Contractor: : Porr Construct SRL; Cost: 1,678,873,121.77 lei (excluding VAT); duration: 16 months for design, 44 months for execution. Contract signed in November 2021. Opening date: 2026
  • Section 5 Curtea de Arges - Pitesti, 30.35km. Contract signed in May 2020; contractor: Astaldi; Cost: 1,710,277,069.34 RON (excluding VAT); duration: 12 months for design, 4 years for execution. Opening date: December 2024 for Bascov - Baiculesti, difference in 2025


Back to A1 sections list


III.Section Sibiu - Orastie

Status: Open

Length: 82.20 km

Opening date: December 2013 for segments 1, 2 and 4, November 2014 and October 2016 (following repairs) for segment 3


The section is split into four segments. Contractors for all four segments were selected in April 2011. Sections 1, 2 and 4 were opened in December 2013, while section 3 was opened in November 2014:

  • Segment 1 Vintisoara - Orastie, 24.11 km: Contractor: Strabag, Cost: 551.04 Million RON
  • Segment 2 Cunta - Vintisoara, 19.75 km: Contractors: Straco Grup and Studio Corona, Cost: 377.78 Million RON
  • Segment 3 Saliste - Cunta, 22.10 km: Contractor: Impregilo, Cost: 604.79 Million RON
  • Segment 4 Sibiu - Saliste, 16.24 km: Contractors: Astaldi, Euroconstruct Trading '98 and Astalrom, Cost: 484.83 Million RON

Back to A1 sections list


IV.Section Orastie - Deva

Status: Open

Length: 32.50 km

Opening date: December 2012 for 14.80 km and June 2013 for the remaining 17.70 km


For this section contractors were selected in November 2010, and were Strabag and Straco. The cost of the section was 220 Million EUR. A section between Simeria and Deva (14.8 km) was opened in December 2012, with the remainder opened in May 2013.


Back to A1 sections list


V.Section Deva - Lugoj

Status: Partially open (segment 1, 15km of segment 2, segment 3 and segment 4), works in progress for route Margina - Holdea on section 2 (13.16km)

Length: 99.50 km

Opening dates: December 2013 for 17 km of segment 1 (Traian Vuia - Balint), December 2015 for the remainder of segment 1 (Balint - Sanovita); 15,08km of segment 2 in Mar 2017; segment 4 in Aug 2019; segment 3 in Dec 2019; 2026 for segment Maringa - Holdea on segment 2


The section is split into four segments:

  • Segment 1 Traian Vuia - Sanovita, 27.62 km: Contractors: Tirrena Scavi, Societa Italiana per Condotte d'Acqua and Cossi Costruzioni, cost: 681.04 Million RON.
  • Segment 2 Cosevita - Traian Vuia, 28.60 km: Contractors: I. for a section of 15.08km: JV Salini SPA and Secol SPA. Cost: 128 Million EUR; II. for remaining section of 13.16km (Margina - Holdea): Spedition UMB SRL - Tehnostrade SRL - SA&PE Construct SRL - Euro-Asfalt d.o.o., cost: 1.82 Billion RON (excl. VAT), design: 11 months, execution: 34 months, contractors selected in September 2022, contract signed in October 2022
  • Segment 3 Ilia - Cosevita, 21.14 km: Contractors: Teloxim Con SRL, Comsa SA, Aldesa Construcciones SA and Arcadis Eurometudes SA. Cost: 132 Million EUR
  • Segment 4 Soimus - Ilia, 22.14 km: Contractors: Tehnostrade, Spedition UMB, Cost: 1,048.53 Million RON (excluding VAT)
A stretch of 10.5 km of motorway A6 Lugoj - Calafat connects A1 motorway (at Balint) to Lugoj bypass.


Back to A1 sections list


VI.Section Lugoj - Timisoara

Status: Open

Length: 35.13 km

Opening date: Segment 1 opened in October 2012, Segment 2 opened in December 2015


The section is split into two segments:
  • Segment 1 Izvin - Giarmata (Timisoara bypass), 9.50 km: Contractors: Spedition UMB, Tehnostade and Carena SpA Impresa di Costruzioni, Cost: 210.36 Million RON
  • Segment 2 Sanovita - Izvin, 25.63 km. Contractors: Tirrena Scavi and Societa Italiana per Condotte D'Acqua. Cost: 94.7 Million EUR. (excluding VAT)
Section 1 was opened in October 2012, while section 2 was opened in December 2015.


Back to A1 sections list


VII.Section Timisoara - Arad

Status: Open

Length: 32.25 km + 8.75 km (Arad Bypass)

Opening date: Dec 2011


Contractors Astaldi and FCC Construccion were selected in 2009. Cost: 194 Million EUR.

Timisoara-Arad section was opened for traffic in December 2011.

The Arad bypass motorway has a length of 8.75 km (and initially included a stretch of 3.5 km connecting Arad to DN7 which were later included in the A11 motorway); 11.3 km (two lanes only) and 1 km (four lanes) were opened in December 2011, with full completion achieved in June 2012. Contractors: FCC and Porr, Cost: 117 Million EUR.


Back to A1 sections list


VIII.Section Arad - Nadlac


Status: Open

Length: 38.88 km

Opening date: Segment 1 and 6km of segment 2 opened in December 2014, July 2015 for the remainder


The section is split into two segments, and contractors were selected in April 2011:
  • Segment 1 Pecica - Nadlac, 22.22 km: Contractors: Astaldi and Max Boegla selected in August 2013 after cancellation of contract awarded in July 2011 to Romstrade, Monteadriano Engenharia e Construcao and Donep Construct. Cost: 248.4 Million RON
  • Segment 2 Arad - Pecica, 16.66 km: Contractors: Astaldi SpA - Max Boegl Romania SRL, contract signed in September 2014 following cancellation of initial contract due to bankruptcy of contractor Alpine. Cost: 89,348,287.63 RON without VAT.

Back to A1 sections list


(C) 130km.ro / Back to Romanian motorway list