130km.ro

Welcome. On this site we present full updated information on Romanian Motorways and motorway projects.



A3 Motorway Bucharest - Bors

Length: 584 km. Status:

Color map: Open (19%); under construction (0%); planned (79%).

The A3 Motorway, also called the Transylvania Motorway, connects Bucharest with the border with Hungary at Bors. Two sections of the motorway are open: Bucharest - Ploiesti (with the exception of 6.5 km still under construction) and Campia Turzii - Gilau. No contractors are selected for any of the remaining sections.


For detailed information please choose a section from the list below:

SectionStatusOpening
I.Bucharest - PloiestiPartially openJuly 2012; 2016 for the remaining 6.5 km
II.Ploiesti - BrasovPlanned2018 (partially)
III.Brasov - Tg. MuresPlanned2016 (partially,estimated)
IV.Tg. Mures - GilauPartially open2009, 2010, 2015
V.Gilau - BorsPlanned2015-2017

I.Section Bucharest - Ploiesti


Status: Under construction

Length: 62 km

Opening date: July 2012 for Moara Vlasiei - Ploiesti and for a partial segment of Bucharest - Moara Vlasiei (Bucharest Ringroad - Moara Vlasiei); 6.5 km to be opened in 2016


  • Segment 1 - 19,5 km: Contractors: Pizzarotti and Tirrena Scavi, Cost: 318.6 Million EUR. Contract will be canceled for the remaining 6.5 km.
  • Segment 2 - 42,5 km: Contractors: Spedition UMB, Euroconstruct Trading and Pa&Co, Cost: 492 Million EUR

Back to A3 sections list


II.Section Ploiesti - Brasov


Status: Planned

Length: 106.6 km

Opening date: 2018 for Comarnic - Brasov


The section is split into two segments: Ploiesti - Comarnic with a length of 48.6 km and Comarnic - Brasov with a length of 58.0 km. The latter is split into two subsections (Comarnic-Predeal and Predeal-Brasov) and is currently tendered for a concession agreement (announced tender winner: Vinci-Strabag-Aktor consortium).


Back to A3 sections list


III.Section Brasov - Tg. Mures


Status: Planned

Length: 161 km


The section is split into three segments: Segment 1A Brasov (Cristian) - Fagaras with a length of 53 km, Segment 1B Fagaras - Sighisoara, 52 km, and Segment 1C Sighisoara - Tg. Mures (Ogra), 56 km. There are no contractors selected for any of these segments, after the Bechtel contract was cancelled.


Back to A3 sections list


IV.Tg. Mures - Gilau


Status: Partially operationa;

Length: 90 km


Opening dates: 2009-2010 for Campia Turzii - Gilau, 2015 for the three segments of Targu Mures - Orga - Campia Turzii

The section is split into two segments. Segment 2A Targu Mures (Ogra) - Campia Turzii, 36 km, is planned but no contractor has been selected after the contract with Bechtel was cancelled; this could be one of the first segments on A3 to be re-tendered.

Segment 2B Campia Turzii - Gilau (Cluj-Napoca Vest), 52 km, is Open (42 km opened in 2009, 10 km opened in 2010).


Back to A3 sections list


V.Gilau - Bors


Status: Partially under construction

Opening dates: 2014-2020 (estimated), 2015 for Gilau - Nadaselu, 2016 for Nadaselu - Mihaiesti, 2017 for Mihaiesti - Suplacu de Barcau, 2016 for Suplacu de Barcau - Bors

Length: 164 km


The section is split into three segments: 3A Gilau (Cluj-Napoca Vest) - Mihaiesti, 24 km, 3B Mihaiesti - Suplacu de Barcau, 76 km, and 3C Suplacu de Barcau - Bors, 64 km. No contractors were selected for any of these sections after the contract with Bechtel was cancelled (except for an 8.7km stretch between Gilau and Nadselu - see below).

The stretch between Gilau and Nadaselu (8.7 km, part of section 3A) is under construction - contract signed with UMB Spedition in April 2013; expected completion: Apr 2015; cost: 258.2 Million RON + VAT.


Back to A3 sections list

(C) 130km.ro / Back to Romanian Motorways list