130km.ro

Welcome. On this site you can view information concerning existing and future Romanian motorways.



A7 Motorway: Ploiesti - Siret

Length: 437km. Status:

Color map: Open (7%); under construction (70%); planned (23%).

Ploiesti - Siret motorway is a proposed motorway following the route Ploiesti - Buzau - Focsani - Bacau - Pascani - Suceava - Siret.

For detailed information please choose a section from the list below:

SectionStatusOpening
I.Bacau Ringroad (partial section)OpenDec 2020
II.Ploiesti - Buzauunder construction2024,2025
III.Buzau - Focsanipartially open, remainder under construction2024
IV.Focsani - Bacauunder construction2025
V. Bacau - Pascaniunder construction2025
VI. Pascani - SuceavaTender in progressn/a
VII. Suceava - SiretPlannedn/a

I.Bacau Ringroad (partial section)

Status: 16.27km open

Length of Bacau Ringroad: 30.70km out of which 16.27km following the route of A7 motorway

Opening Date: Dec 2020


The contract for the entire length of Bacau Ringroad (30.70km) was signed with the consortium Spedition - UMB SRL - Tehnostrade SRL in August 2018, price: 668,330,294.63 RON (excluding VAT).


Back to A7 sections list

II.Ploiesti - Buzau

Status: Under construction

Length: 63.25km

Opening Date: 2024 for sections 1 and 2, 2025 for section 3


This route is split into three sections:
  • Section 1 Dumbrava (A3) - Mizil, 21.00km. Contractor selected in April 2022: the consortium Impressa Pizzarotti & C SPA - Pizzarotti SA - Retter Project Management SRL, Price: 1.468.550.055,22 RON excluding VAT, construction duration: 20 months. Contract signed in June 2022. Estimated opening date: 2024
  • Section 2 Mizil - Pietroasele, 28.35km. Contractor selected in February 2022: the consortium Coni SRL - Trace Group. Price RON 1.25 billion (excl. VAT), construction period: 20 months. Contract signed in June 2022. Estimated opening date: 2024
  • Section 3 Pietroasele - Buzau, 13.90km. Contractor selected in October 2023: The consortium Nurol Inşaat Ve Ticaret A.S. - Makyol Insaat Sanayi Turizm Ve Ticaret A.S., price: 1.09 billion RON (excl. VAT). Execution duration: 20 months. Contract signed in November 2023. Estimated opening date: 2025


Back to A7 sections list

III.Buzau - Focsani

Status: Section 4 open, remainder under construction

Length: 82.44km

Opening Date: 2024


This route is split into four sections:
  • Section 1 Buzau - Vadu Pasii, 4.60km. Contractor selected in August 2022: the consortium SA&PE CONSTRUCT SRL – SPEDITION UMB SRL – TEHNOSTRADE SRL, price 689,285,996.26 RON (excl. VAT), execution duration: 20 months. Contract signed in Sep 2022. Estimated opening date: 2024
  • Section 2 Vadu Pasii - Ramnicu Sarat, 30.80km. Contractor selected in September 2022, confirmed in December 2022: the consortium SC SA & PE CONSTRUCT SRL – S.C. SPEDITION UMB S.R.L. – S.C. TEHNOSTRADE S.R.L. – S.C. INTERTRANSCOM IMPEX S.R.L., price 1.317 billion RON (excl. VAT), execution duration: 26 months. Contract signed in Januar 2023. Estimated opening date: 2024
  • Section 3 Ramnicu Sarat - Mandresti Munteni, 36.10km. Contractor selected in September 2022, confirmed in December 2022: the consortium SC SA & PE CONSTRUCT SRL – S.C. SPEDITION UMB S.R.L. – S.C. TEHNOSTRADE S.R.L. – S.C. INTERTRANSCOM IMPEX S.R.L., price 1.469 billion RON (excl. VAT), execution duration: 26 months. Contract signed in Januar 2023. Estimated opening date: 2024
  • Section 4 Mandresti Munteni - Focsani Nord, 10.94km. Contractor selected in August 2022: the consortium SA&PE CONSTRUCT SRL – SPEDITION UMB SRL – TEHNOSTRADE SRL, price 763,720,833.05 RON (excl. VAT), execution duration: 20 months. Contract signet in Sep 2022. Opened in November 2024


Back to A7 sections list

IV.Focsani - Bacau

Status: Under construction

Length: 95.90km

Opening Date: 2025


This route is split into three sections:
  • Section 1 Focsani - Domnesti Targ, 35.60km. Contractor selected in November 2022: the consortium Spedition UMB SRL - SA&PE Construct SRL - Tehnostrade SRL, execution duration: 30 months. Contract signed in December 2022, Estimated opening date: 2025
  • Section 2 Domesti Targ - Racaciuni, 38.78km. Contractor selected in November 2022: the consortium Spedition UMB SRL - SA&PE Construct SRL - Tehnostrade SRL, execution duration: 30 months. Contract signed in December 2022, Estimated opening date: 2025
  • Section 3 Racaciuni - Bacau, 21.52km. Contractor selected in November 2022: the consortium Spedition UMB SRL - SA&PE Construct SRL - Tehnostrade SRL, execution duration: 30 months. Contract signed in December 2022, Estimated opening date: 2025
Total price for all three sections: RON 6,513,554,258.24 excl. VAT


Back to A7 sections list

V.Bacau - Pascani

Status: Under construction

Length: 77.39km

Opening Date: 2025


This route is split into three sections:
  • Section 1 Saucesti (Bacau) - Trifesti Targ, 30.30km. Contractor designated in December 2022: the consortium SA&PE CONSTRUCT SRL – SPEDITION UMB SRL – TEHNOSTRADE SRL, price: 1.63 billion RON (excl. VAT), execution duration: 30 months. Contract signed in Feb 2023
  • Section 2 Trifesti - Gheraiesti, 18.99km. Contractor designated in December 2022: the consortium SA&PE CONSTRUCT SRL – SPEDITION UMB SRL – TEHNOSTRADE SRL, price: 1.28 billion RON (excl. VAT), execution duration: 30 months. Contract signed in Feb 2023
  • Section 3 Mircesti - Pascani, 28.09km. Contractor designated in December 2022: the consortium SA&PE CONSTRUCT SRL – SPEDITION UMB SRL – TEHNOSTRADE SRL, price: 1.76 billion RON (excl. VAT), execution duration: 30 months. Contract signed in Feb 2023


Back to A7 sections list

VI.Pascani - Suceava

Status: Tender in progress

Length: 61.97km

Opening Date: -


This route is split into two sections:
  • Section 1 Pascani - Roscani, 33.00km
  • Section 2 Roscani - Suceava Airport, 28.97km

Back to A7 sections list

VII.Suceava - Siret

Status: planned

Length: 41.00km

Opening Date: -



Back to A7 sections list

(C) 130km.ro / Back to Romanian Motorways list