 A8 Union Motorway: Targu Mures - Iasi - Ungheni
Length: 305km. Status:  
Color map:  Open (0%);  under construction (18%);  planned (82%).
A8 Motorway, also known as Union Motorway, is a proposed motorway following the route Targu Mures - Ditrau - Poiana Largului - Targu Neamt - Pascani - Targu Frumos - Iasi - Ungheni.
For detailed information please choose a section from the list below:
I.Targu Mures - Miercurea Nirajului
Status: under construction
Length: 24.40km
Opening Date: 2026
Contractor: NUROL INSAAT VE TICARET A.S., price: RON 2.46 billion (excl. VAT), design duration: 6 months, construction duration: 24 months, contract signed in February 2024.
|
Back to A8 sections list
II.Miercurea Nirajului - Leghin
Status: Tender in progress
Length: 161.50km
Opening Date: -
This route is split into six sections, as follows:
- Section 1b Miercurea Nirajului - Sarateni, 23.40km. Tender launched in April 2024
- Section 1c Sarateni - Joseni, 32.40km. Tender launched in October 2024
- Section 1d Joseni - Ditrau, 14.40km. Tender launched in October 2024
- Section 2a Ditrau - Grinties, 37.90km. Tender launched in October 2024
- Section 2b Grinties - Pipirig, 34.10km. Tender launched in November 2024
- Section 2c Pipirig - Vanatori Neamt (Leghin) 19.30km. Tender launched in May 2024.
|
Back to A8 sections list
III.Leghin - Targu Neamt
Status: Under construction
Length: 29.91km
Opening Date: 2026
Contractor selected in July 2023: the consortium SA&PE CONSTRUCT SRL – SPEDITION UMB SRL – TEHNOSTRADE SRL, price: RON 1.56 billion, design duration: 6 months, construction duration: 24 months. Contract signed in September 2023.
|
Back to A8 sections list
IV.Targu Neamt - Iasi - Ungheni
Status: partially tendered, remainder planned
Length: 88.77
Opening date: -
This route is split into five sections, as follows:
- Section 1 Targu Neamt (Motca) - Targu Frumos, 27.00km. Tender launched in January 2025
- Section 2 Targu Frumos - Letcani, 28.60km. Tender launched in February 2025
- Section 3 Letcani - Iasi, 17.70km. Planned
- Section 4 Iasi - Golaiesti, 12.70km. Planned
- Section 5 Golaiesti - Ungheni Bridge, Planned.
This route ends with the Ungheni Bridge (1.1km) over Prut river.
|
Back to A8 sections list
V.Ungheni Bridge
The Ungheni Bridge (1.1km) over Prut river.
Status: Under construction
Length: 1.1km
Opening Date: 2026
Contractor: Ness Proiect Europe SRL, contractor selected in July. Price: RON 151.68 million. Duration: 6 months for design, 18 months for execution. Contract signed in September 2024.
|
Back to A8 sections list
(C) 130km.ro / Back to Romanian Motorways list
|
|