DEx12 Expressway: Craiova - Pitesti
Length: 121.25 km. Status:
Color map: Open (59%); under construction (41%); planned (0%).
DEx12 is the first expressway under construction in Romania for the route Pitesti - Slatina - Craiova, with a total planned length of 121.18km.
For detailed information please choose a section from the list below:
I.Craiova - Robanesti
Status: Under construction
Length: 17.70km
Opening Date: 2024
Contractor: Tirrena Scavi SpA, cost: 358,179,480.69 RON excluding VAT. Contract signed in December 2018, design duration: 12 months, execution duration: 24 months. Contract canceled in December 2022. New tender launched in March 2023. New contractor selected in June 2023 - the consortium OZALTIN INSAAT TICARET VE SANAYI AS – STRADE BAUUNTERNEHMUNG SRL – VISIO CONSTRUCTION WORKS SRL, price: 439.29 million RON, execution duration: 18 months. Contract signed in August 2023.
|
Back to DEx12 sections list
II.Robanesti - Slatina
Status: Open
Length: 39.85km
Opening Date: April 2023 for lot 1, July 2022 for lot 2
The section consists of two lots:
- Lot 1: Robanesti - Piatra Olt, 18.50km, contractor: consortium consisting of SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL - Consitrans SRL, cost: 661,452,009.54 RON excluding VAT. Contract signed in December 2018, design duration: 12 months, execution duration: 24 months. Opened in April 2022
- Lot 2: Piatra Olt - Slatina, 21.35km, contractor: consortium consisting of SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL - Consitrans SRL, cost: 661,452,009.54 RON excluding VAT. Contract signed in December 2018, design duration: 12 months, execution duration: 24 months. Opened in July 2022
|
Back to DEx12 sections list
III. Slatina - Colonesti
Status: Open
Length: 31.75km
Opening Date: Dec. 2023
Contractor selected in June 2020: the consortium SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price: 999.41 Million RON (excluding VAT), design duration: 12 months, execution duration: 24 months. Contract signed in September 2020.
|
Back to DEx12 sections list
IV. Colonesti - Pitesti (A1)
Status: Under construction
Length: 31.88km
Opening Date: 2024
Contractor selected in June 2020 and confirmed in February 2021 and in July 2021: the consortium SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price: 617,080,915.60 Million RON (excluding VAT), design duration: 12 months, execution duration: 24 months. Contract signed in August 2021.
|
Back to DEx12 sections list
(C) 130km.ro / Back to Romanian Motorways list
|
|