Welcome. On this site you can view information concerning existing and future Romanian motorways.



DEx6 Braila - Galati Expressway and Braila Bridge

Length: 12.29km. Status:

Color map: Open (0%); under construction (100%); planned (0%).

This expressway will connect the cities of Braila and Galati and has a planned length of 12.29km. The contractor was selected in September 2020 and is the consortium SA & PE Construct SRL - Spedition UMB - Tenostrade SRL, price: 371,416,131.09 RON excluding VAT, execution duration: 10 months for design, 24 months for execution, opening date: 2024. Contract signing took place in April 2021.

The route of the expressway is continued with a bridge over the Danube between Braila and Smardan in Tulcea county, which was opened in July 2023. This bridge is not part of the Braila - Galati expressway. The contract was signed in January 2018 with the consortium Astaldi - IHI Infrastructure Systems, price: 1,995,932,260.25 RON excluding VAT, execution duration: 12 months for design, 36 months for execution, opening date: July 2023.

For detailed information please choose a section from the list below:


SectionStatusOpening
I.Braila - GalatiUnder construction2024
II.Braila BridgeOpenJul 2023

I.Braila - Galati

Status: Under construction

Length: 12.29km

Opening Date: 2024


Contractor: The consortium SA & PE Construct SRL - Spedition UMB - Tenostrade SRL, price: 371,416,131.09 RON excluding VAT, execution duration: 10 months for design, 24 months for execution, opening date: 2024. Contract signed in April 2021.

Back to DEx6 sections list

II.Braila Bridge

Status: Open

Length: 1.97km

Opening Date: Jul 2023


Contractor: The consortium Astaldi - IHI Infrastructure Systems, price: 1,995,932,260.25 RON excluding VAT, execution duration: 12 months for design, 36 months for execution, opening date: 2022. Contract signed in January 2018.

Back to DEx6 sections list

(C) 130km.ro / Back to Romanian Motorways list